Construction Wear Point Wind Farm well underway


Construction of the 4-turbine Wear Point Wind Farm at SemLogistics' oil storage facility near Milford Haven, Wales, is well underway. Local contractors are busy constructing the access tracks, substation and a bridge needed to provide access to the two most westernly turbine locations. Excavations and ground works are in full swing to prepare for foundation pouring, scheduled for later this month.

Joint owners John Laing and Infinergy are delighted with the progress made so far. It is expected that the four REpower MM82's will be fully operational towards the end of this year.

<< Back to news